A quick construction update. Wattle Road is behind schedule, however on track to be ready for day 1, 2020. The fences which have just been erected on the east side of MPAC are for the construction of the new driveway under MPAC. This will allow us to fill in the existing driveway and commence the landscaping for College Square in the heart of the College.

This week the builders have moved into the back of the Library for the refurbishment of spaces to provide 6 new classrooms to make a home for our Year 9 students.

There will be some major works in front of MPAC over the Christmas break. We are making a new entrance to the College off Morris Road to extend the drop-off zone and constructing an awning to provide all-weather drop-off in front of MPAC.

The Christmas break will be a busy time around campus.